Rock Creek Mine gets cautious, partial approval

Southern Cabinet Mountains, as seen from Swede Mountain, near Libby
Southern Cabinet Mountains, as seen from Swede Mountain, near Libby

Hecla Mining’s proposed Rock Creek Mine near the Cabinet Mountains Wilderness received partial approval from the US Forest Service — enough to build an adit and do some environmental work. By and large, this is a victory for opposition environmental groups . . .

Opponents and proponents of a proposed copper and silver mine in Sanders County are both celebrating after the U.S. Forest Service announced it would issue only a partial approval for the project in an upcoming Record of Decision.

Conservation groups say that the decision to withhold a full development permit for the Rock Creek Mine proves that a massive industrial project should not be developed beneath a wilderness area for fear that it will dewater the land above. But officials with Hecla Mining Company, the Coeur d’Alene-based mining company heading up the project, said that a phased approval has always been part of the plan.

In a letter dated Oct. 31, Deputy Regional Forester David E. Schmid announced that the final Record of Decision would only approve phase 1 of the Rock Creek Project, allowing the construction of a mine adit and an environmental evaluation of the site, which is located near Noxon.

Read more . . .